LIST OF JOBS
From The Star And Shadow Cinema Wiki
- Widening door in bar - Debbora and her contacts, day 1 and 2, bringing their own materials.
- Installing telephone system for wheelchair recess. - [here is an example
1 person 1/2 day.
- sewing and Putting up drape/ lighting bars in the bar - Jona interested in doing the scaff bars. Drape already in the cinema? Need Sewing machine which Jona can provide. Amanda has offered to do the sewing.
2 people 3 days.
- Extending lighting flex on pendants in bar - 50m 2core 5a flex,
1 person 1 day
- Building the bar - Timber - 3x2, 2x2, 18mm ply, 6mm hardboard, fixings, paint, 8mm perspex for bar top and backs of shelves, light fittings etc.
4 people 3 days.
- Painting hammerite on the steel structure - wire brush to prepare surface, 1litre hamerite.
1 person, 5hours.
- Fire proofing ceiling of the heating plant room - plaster board, scrim tape, bag of joint filler, 25mm galvanized clout nails.
3 people, 1 day (Sat 2nd) including Keith.
- Fixing all the holes and fire proof foaming anywhere needed -
2 persons 1 day.
- Bar furniture - making benches for bar - 2x2, 18mm ply, foam, fabric, fire retardant. -
4 people 3 days.
- Painting and decorating the bar and fire corridor - 2 coats ochrey yellow (ceiling), (20l), aluminium primer, 5" cutting in brush, bunch of rollers, 4 extension arms, paint buckets,
2 people, 4 days.
- Painting and decorating the office
6 people 1 week
- Ebaying stuff - ongoing, 1 or 2 people
- Sign on the front door and rennovation of the existing blackboard on the outside and making large poster boxes on hinges for front door. - angle iron, hinges, bolts, perspex (Jona), maybe Shimmersign if we agree,
2 people 2 days.
- Signs in the hallway - 18mm ply, jigsaw, paint? keep closed and keep clear stickers
2 people 2 days
- Painting the ceiling towards the toilets - using up excess paint that is in the back.
2 people 1 day.
- Painting the corridor into the projection booth - included in bar ceiling calculation.
- Tidying office - included in painting and decorating office calculation.
- Skipping stuff - ongoing, x2 one at beginning one at end. - check envirocall for legalities of getting rid of stuff.
- Painting the lobby
1 artist 3 dayts
- Kitchen area (thoughts on what are here here)
2 people 3 days
- Electrics into dark room
prior to building festival
- Plumbing into darkroom
prior to building festival
- Ventilation into dark room
2 people in early stages of festival - Ian B and 1 other. - 3 days
- Fixing Piano - being taken away when sewing machine is dropped off.
1 person - Ian B. over the next while.
- Painting doors and Flooring in the mens toilet to combat smell and painting walls and floor in staff toilet. - egg shell for doors, industrial floor paint?
2 people 1.5 days.
- replacing toilet seats - - 10x heavy use toilet seats (P.T.S £12 each)
1 person 1 day
- Electrics into small office. - included in dark room electrics.
- Fixing light fittings in hallways - Job for Derek some other time.
- Building 30x40" steel and perspex boxes for front door. - angle steel (7.5m), 4x hinges, 4x 6"bolts and wing nuts. 8x4' sheet perspex.
1 person 1 day.
- Cleaning hallway including steel trusses - hoover, scaff tower.
2 people 1/2 day.
- Finishing off box office - paint, timber for shelves?
1 person 1 day.
Total persons - 45, Total days - 43 = 45 people days to do So if 45 people work it will take 1day. If 1 person - 45days. If 15people help it will be done in a week.