Current building jobs and their status

From The Star And Shadow Cinema Wiki

Jump to: navigation, search
  • make gate at back - dont bother

Priority Jobs:


Architraves - hmmm

Planing doors - done

filling corners - still needs doing

fire retardant foam - on list for building fest

sanding filling painting - toilet corridor, stairs, outside projection booth, above entrance way. - on list for building fest

thick perspex in box office - unnecessary

window ceiling in office - done

electrics in box office - done

electrics in the long space - later

cleaning the walls and steel work in the long space - on list of building fest

chopping up pallets to take away to burn - done

getting rid of green chairs - to skip - get permit off jonathan miles - done

clean yard - done

painting the new month sign - building fest

painting the front of the bar - building fest

upgrading the back of the bar. - building fest

plastering scraggy door openings - building fest

cleaning the toilets/ mopping - done

mopping the long space - done

skirting board in corridors - building fest

second coat of paint inthe toilet floors - hmmm

second coat of white in gents - ignore

cleaning paint of the toilet seats and doors - done

painting the skirting int he toilets - maybe

making masking for the screen - done

windows in the booth + third window. - needs attention

cabling for projector and bracket - done


Back fire exit needs finishing off. "Essential for fire compliance" - big job

Back gate. Need the door

Door buzzer. - needs researching and buying - part of operating licence - Marek to finish off?

Paint floors. -second coat for bar and toilets. Need four day gap really. Box office and whole front section needs making made fire retardant. - "essential for fire compliance"

Need separate casing room for boiler that hasnt got in yet. Essential for building control

Decide on coving or not in cinema not but corners need caulking ask Andy Slater potentially interested in designing and making one in the long term.

Paint toilets nearly done not fire necessity - need gloss for skirting and creatives

Clean big corridor and beams in it. not fire worry but building will forever be dusty without. - building fest

Need vent putting in 'spare room' Quote coming from AC Ventilation - ian?

need permanent lectric in both spare rooms. building fest

Skimming escape corridor office side of it. - painting

Decorative painting in the bar. - building fest

Nosing on carpets in cinema- waiting for sean. - done

Inductive loop in the cinema needs bits to go with it. yes yes yes

rubber washers so can put in seats from edinburgh rather than green ones at backf auditorium - ignore

Structural docs in order cinema ceiling, corridor ceiling, fire escape adjustments etc.

curtains around new screen (must be fire proof) - done

Cinema mural painted - under direcion of Flora and Susie - done

sound insulation complete on Bar ceiling aand fire proof wall in ceiling compartment. - building fest